The project involves the construction of a new eight-story patient care tower and three-story connection, as well as demolition of some existing space and renovations to the existing hospital. The project will add up to approximately 550,000 square feet to the existing hospital. The project also involves renovation works of approximately 100,000 square feet of select areas within the existing hospital.
Why Distech Controls technology?
Distech Controls solutions were chosen because of their openness, integration capabilities, and future expansion.
Solutions fitted in the building:
A variety of Distech product solutions will be implemented in this project:
- EC-Net Supervisor
- 600+ Eclypse controllers
- 100+ ECB controllers
- 1200+ Room Sensors
- Third-party field devices
Stakeholders:
System Integrator: Modern Niagara
General Contractor: Ellis Don
Owner: Infrastructure Ontario