Lithonia Lighting® Aluminum Pole Lead Time Reduction

September 8, 2023 Nikki Figura

Gone are the days of 12-week Aluminum pole lead times! All painted aluminum poles have had their lead times reduced! Anodizing will add 12 weeks.

  • SSA: 6-8 weeks
  • RSA: 6-8 weeks
  • RTA: 8 weeks
  • Other Aluminum: 8-10 weeks

Additional updates for steel pole lead times include:

  • SSS QS: 10 days with a 15-day delivery date (down from a 21-day delivery date)
  • SSS: 4 weeks
  • STS: 7-8 weeks
  • RTS: 7-8 weeks
  • Other Steel: 7-8 weeks

*Note: Orders of 25 or more, configurations with options and requiring RFA will add additional time. Please consult Product Support for details.